Test - Launch Now

The primary objectives of the Test stage for a Launch Now activation are to:

  • Complete configuration testing
  • Complete payroll parallel testing (if applicable)

Some activities in this stage depend on the products deployed. Assume that all activities in the Test stage are required unless otherwise noted.

 

Testing Kickoff

  • Attend and actively participate in the testing kickoff

End to End Testing

  • Conduct End to End Tests based on test scenarios

Payroll: Parallel Testing (if applicable)

  • Conduct two cycles of Payroll Parallel Test

Data Validation & Correction

  • Validate customer data and correct as needed

Program Type

Launch Now Test Stage